Question: Apply PERT method for project planning. Activity Immediate Predecessors 1 2 Activity No. 1 2 3 4 5 6 7 8 9 10 2 Time

Apply PERT method for project planning.

Apply PERT method for project planning. Activity

Activity Immediate Predecessors 1 2 Activity No. 1 2 3 4 5 6 7 8 9 10 2 Time (weeks) 3 2 2 6 3 2 4 5 Collect requirements Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and Dokument Install 3 3,4 4,5 6,7 7 8,9 7 2