Question: Apply the Hungarian Method to the problem. What is an optimal assignment? What is the total distance associated with an optimal assignment? A construction company

Apply the Hungarian Method to the problem. What

  • Apply the Hungarian Method to the problem.

  • What is an optimal assignment? What is the total distance associated with an optimal assignment?

A construction company has four large bulldozers located at four different garages. The bulldozers are to be moved to four different construction sites. The distances in miles between the bulldozers and the construction sites are given below. Site A Site B Site C Site D Bulldozer 1 90 75 75 80 Bulldozer 2 35 85 55 65 Bulldozer 3 125 95 90 105 Bulldozer 4 45 110 95 115 The problem is to determine how the bulldozers are to be moved to the construction sites with the total distance travelled minimized

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!