Question: Apply the PERT system (weighted average; Program Evaluation and Review Technique) of estimating the amount of time a particular task will take. The estimated times

Apply the PERT system (weighted average; Program Evaluation and Review Technique) of estimating the amount of time a particular task will take. The estimated times for this task are as follows: Pessimistic = 5 days; Realistic = 3.5 days; Optimistic = 2.5 days. Calculate the estimated time using the PERT method. Be sure to show the formula not just the answer.