Question: Apply the right method for solving problems in a project / business feasibility in an industrial company in a comprehensive manner No. Activity Predecessors Estimated

Apply the right method for solving problems in a project / business feasibility in an industrial company in a comprehensive manner

No. Activity Predecessors Estimated Time (Month)

Time

Optimistic (a)

Time Normal (m)

Time

Pessimistic (b)

1 A 11 15 16
2 B A 13 16 18
3 C B 14 17 22
4 D B 16 17 19
5 E B 15 18 21
6 F C 12 19 20
7 G C 11 13 15
8 H D,E 18 20 23
9 I F,G,H 22 23 26

Questions:

a. Create a Network Planning

b. Determine the activity path

c. Calculate Expected Time (te)

d. Determine the critical path

e. Calculate Variance (vt)

f. Calculate Standard Deviation (St)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Law Questions!