Question: Apply the right method for solving problems in a project / business feasibility in an industrial company in a comprehensive manner No. Activity Predecessors Estimated
Apply the right method for solving problems in a project / business feasibility in an industrial company in a comprehensive manner
| No. | Activity | Predecessors | Estimated Time (Month) | |||
| Time Optimistic (a) | Time Normal (m) | Time Pessimistic (b) | ||||
| 1 | A | 11 | 15 | 16 | ||
| 2 | B | A | 13 | 16 | 18 | |
| 3 | C | B | 14 | 17 | 22 | |
| 4 | D | B | 16 | 17 | 19 | |
| 5 | E | B | 15 | 18 | 21 | |
| 6 | F | C | 12 | 19 | 20 | |
| 7 | G | C | 11 | 13 | 15 | |
| 8 | H | D,E | 18 | 20 | 23 | |
| 9 | I | F,G,H | 22 | 23 | 26 | |
Questions:
a. Create a Network Planning
b. Determine the activity path
c. Calculate Expected Time (te)
d. Determine the critical path
e. Calculate Variance (vt)
f. Calculate Standard Deviation (St)