Question: Apply the SPT (shortest processing time) rule to find the processing sequence of jobs. What is Job Bs waiting time? Apply the EDD (earliest due
Apply the SPT (shortest processing time) rule to find the processing sequence of jobs. What is Job Bs waiting time?
Apply the EDD (earliest due date) rule to find the processing sequence of jobs. What is Job Bs waiting time?

Each of the seven jobs needs to go through a work center named "La La land". The manager, Mia Dolan's goal is to find the optimum sequence of jobs to minimize the total makespan (flow time). We assume that all the jobs are ready at t=0 (when you open your work center). Q5B-1. Apply the SPT (shortest processing time) rule to find the processing sequence of jobs. What is Job B's waiting time? Q5B-2. Apply the EDD (earliest due date) rule to find the processing sequence of jobs. What is Job B's waiting time? 1