Question: Applying PERT network analysis what is the expected value duration of a task with a pessimistic time of 24, optimistic time of 7 and most
Applying PERT network analysis what is the expected value duration of a task with a pessimistic time of 24, optimistic time of 7 and most likely time of 14?