Question: a)Prepare two type of Flow Process Chart (Man+Material type) for the following activities Nr Time 1 Load bags of cement into truck at rail way
- a)Prepare two type of Flow Process Chart (Man+Material type) for the following activities
| Nr |
| Time |
| 1 | Load bags of cement into truck at rail way yard | 3 hours |
| 2 | Wait for transport release from the supervisor | 1/2 hr. |
| 3 | Transport to covered storehouse by truck | 1 hr. |
| 4 | Unload at warehouse | 2 hr. |
| 5 | Inspect for damaged bags | 1/2 hr. |
| 6 | Retain in storage until needed in plant 2 | 1 to 10 days |
| 7 | Transfer to plant 2 using fork lift truck | 1 hr. |
- What are the obvious problems in the job and how can they be improved? Write a narrative summary (a main body paragraph ranges from 3-5 sentences) that describes how your suggestion could address each of the workflow problems listed.