Question: 2. Is this optimal solution? Is there alternate optimal solution? Is the solution feasible? Is the solution degenerate? What is the optimal product mix and
2.
Is this optimal solution? Is there alternate optimal solution? Is the solution feasible? Is the solution degenerate? What is the optimal product mix and optimal profit?
(10 Marks)
M/s Motwani limited have taken up a special project consisting of 10 activities whose three-point time estimates are listed in the table below. Activities are marked with their node numbers.
1-2 1 2 3 1-3 1 2 3 1-4 1 2 3
Activity
Time Estimates in weeks
Optimistic
Most Likely
Pessimistic
Internal Assignment Applicable for September 2022 Examination
2-5 4 9 20 3-5 2 5 14 3-7 3 6 15 5-7 1 2 9 4-6 2 4 6 6-7 3 3 3 7-8 4 4 4
1. Find Expected time, variance and standard deviation of each activity
2. What is the probability that the project will not be completed in 20 weeks?
3. If the project includes a penalty clause of Rs.1,000 per week for any delay beyond 19
weeks then what is the probability of paying a penalty of more than Rs. 5000?
Step by Step Solution
3.31 Rating (163 Votes )
There are 3 Steps involved in it
1 Activity in weeks Optimistic Most Likely 12 13 14 25 Time Estimates 35 37 57 46 67 78 1 1 1 4 2 3 1 2 3 4 Pessimistic 2 2 2 9 5 6 2 4 3 4 optimistic ... View full answer