Question: Arrange Jobs in the appropriate order for processing using the SPT and the LPT. Determine the following for both the SPT and LPT i. Average

-
Arrange Jobs in the appropriate order for processing using the SPT and the LPT.
-
Determine the following for both the SPT and LPT
| i. | Average Completion time |
|
| ii. | Average Job lateness, and | |
| iii. | Average number of jobs in the machine centre |
|
c. Based on a comparison of the metrics that you have calculated in part ii above, which of the rules would you recommend for use in the machine shop?
The following jobs are waiting to be processed at the same machine centre. Assume that all jobs Arrive on day 275 Duration (days) Job M | Table 6 Due Date 313 312 325 314 314Step by Step Solution