Question: Arvind Pontis, has been appointed project manager for a consumer products company. The project's task is a relaunch of an established brand. He estimates that
Arvind Pontis, has been appointed project manager for a consumer products company. The project's task is a relaunch of an established brand. He estimates that the most likely time to complete a project is 24 days (assuming predictable delays and ignoring unlikely scenarios that will either decrease or increase the time). His optimistic prediction for the project is 14 days (assuming that there are none of the usual delays). His pessimistic prediction for the project is 58 days (assuming that all possible delays occur). The expected time for the project is: Question 30Select one: A. 42 Days B. 28 Days C. 20 Days D. 50 Days Jump to
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
