Question: As a construction project manager who recognizes your ability to leave others better than you found them, you're always ready to help those who could
As a construction project manager who recognizes your ability to leave others better than you
found them, you're always ready to help those who could benefit from your tutelage. One of
your assistant project managers brings you the earned value report below. Your cursory glance
shows the report is incomplete and needs some work youre not that surprised though as this
assistant got his degree from some school in Austin:
Calculate the missing information and complete the table above.
The latest project report reflects the following data:
$
$
ACWP$
BAC$
Original length of the project months
Given this information, calculate the following:
a What are the values for I and I
b What is the expected cost at completion EAC
c How much money will be needed from the time of report to complete the project?
d What is the cost variance at completion?
e Using SPI, what is the new expected length of the project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock