Question: As a final check point on utilizing a PDM as a way to sequence and determine the length of a project, using the following information:

As a final check point on utilizing a PDM as a way to sequence and determine the length of a project, using the following information: 1. Calculate the forward pass 2. Calculate the backward pass 3. Determine the length of the project 4. Identify the activities on the Critical Path Activity B D E F G H KOLL BUSINESS CENTER County Engineers Design Department Description Preceding Activity Application approval None Construction plans Traffic study Service availability check A Staff report B, C Commission approval B,C,D Wait for construction F Occupancy Activity Time 5 15 10 5 15 10 170 35 E, G