Question: As a high - profile project manager for nuclear power projects, Theodore has come to the realization that incorporating project changes into the schedule throughout
As a highprofile project manager for nuclear power projects, Theodore has come to the realization that
incorporating project changes into the schedule throughout the project is imperative if he is going to keep
the project on schedule. By utilizing network diagrams, he is able to track the scheduling and execution
of the various tasks throughout the process. When performing a backward pass analysis of a project
schedule, he knows that it is important to identify and evaluate all of the paths of activities that have
A Negative slack
B Positive slack
C No slack
D A critical success factor