Question: As a new owner's representative for a large public school district program, there are greater than $ 3 0 0 million of bonds available
As a new owner's representative for a large public school district program, there are greater than $ million of bonds available for constructing new K facilities over a fouryear period. All construction contracting was recently consolidated at municipal purchasing and the school facilities division was restructured due to inefficient operations. The district has assigned the master program scheduling responsibility to youyour firm. The schedule will include
milestone schedules for each of the schools.
predesign and design phase activities only.
predesign phase activities only.
detailed project schedules for each of the schools.