Question: As a project engineer, you received the AW analysis below from the finance department. It is for a new piece of equipment you ordered some
As a project engineer, you received the AW analysis below from the finance department. It is for a new piece of equipment you ordered some months ago. You were told the interest rate used was 10% per year, but no first cost or projected salvage value was provided and you want to know them. Determine the values of P and S using the AW values for the year 1. Note: The AW values are equivalent values through the given year, not costs for the single year.
| Years Retained | AW of First Cost, $ | AW of Operating Cost, $ per Year | AW of Salvage Value, $ |
| 1 | 51,700 | 15,000 | 35,000 |
| 2 | 27,091 | 17,000 | 13,810 |
| 3 | 18,899 | 19,000 | 6,648 |
| 4 | 14,827 | 21,000 | 4,309 |
| 5 | 12,398 | 23,000 | 2,457 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts