Question: As a project manager in an IT Project that is responsible for building a new e-service for the Ministry of Interior (MOI) , you are
- As a project manager in an IT Project that is responsible for building a new e-service for the Ministry of Interior (MOI) , you are faced with two risks with a 20% and 15 % chance of occurring. Those risks will cost you 10,000 SR and 20,000 SR respectively. What is the expected monetary value of these risk events? (10 marks)