Question: As a project manager, Mary is managing 1 2 different projects. She realized something very interesting related to them. Sometimes they present some unique and
As a project manager, Mary is managing different projects. She realized
something very interesting related to them. Sometimes they present some
unique and particular rules, like the ones for projects #: and She
concluded that neither project nor project is selected unless project is
selected.
For integer programming problems, which one of the alternatives listed
below correctly models this situation?