Question: As a Project Manager, you are managing a project that has fourteen deliverables from outside contractors. One contractor forgot to acquire a certificate of occupancy
As a Project Manager, you are managing a project that has fourteen deliverables from outside contractors. One contractor forgot to acquire a certificate of occupancy from the city for a building to be used as a result of the project. The city building inspector is now requesting to see the certificate of occupancy before allowing people to move into the building. Who is ultimately responsible for acquiring this deliverable (Certificate)?
A) Project Manager
B) City inspector
C) Plumber
D) Con tractor
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts