Question: As a project manager, you estimate a task to take two days. Your team actually took five days to complete the task. What describes the
As a project manager, you estimate a task to take two days. Your team actually took five days to complete the task. What describes the tendency that caused you to underestimate the time for the task?
point
Feedback fallacy
Opinion bias
Planning fallacy
Pessimism bias