Question: As a project manager, your new project has an estimated cost of $ 1 0 , 0 0 0 . You decide to include an
As a project manager, your new project has an estimated cost of $ You decide to include an extra so the final total budget is $ This gives you an additional $ to help smooth over any particularly expensive underestimates in the estimated cost budget. What is this an example of
Calculating the variance against baseline
Calculating the estimate at completion EAC
Forecasting
The reserve analysis technique