Question: As a project manager, you're identifying task dependencies. Task B cannot start until Task A has started. Which type of dependency does this situation represent?
As a project manager, you're identifying task dependencies. Task B cannot start until Task A has started. Which type of dependency does this situation represent?
Finish to Finish FF
Start to Start SS
Start to Finish SF
Finish to Start FS