As George Harman of Centralia Construction Corporation (CCC) reviewed the drawings and cost estimates for the...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
As George Harman of Centralia Construction Corporation (CCC) reviewed the drawings and cost estimates for the Myerson Industries plant expansion, he wondered how aggressively he should bid on the project. The current recession had taken a huge bite out of his business, and the Myerson contract would certainly brighten his rather gloomy view of the future. CCC was a family-run, general contracting firm specializing in the construction of commercial structures in south-central Illinois. Founded 30 years ago by George Harman's father, the business had prospered until the recent recession. For the first time in years, there was no backlog of projects, and layoffs had occurred. Although the firm was not in serious financial trouble, more work would be welcomed. Myerson Industries was a highly successful, fast-growing firm specializing in low-cost printers for use with personal computer systems. The Myerson plant was located approximately 50 miles from CCC's offices in Centralia, Illinois. Recently, Roger Myerson had informally inquired if CCC would be interested in bidding on a contract for an addition to the Myerson facility. Harman indicated that he would look forward to the opportunity to submit a bid. Last week the architectural drawings arrived with a cover letter stating that a fixed-price contract would be preferred; that is, the contractor would be paid an agreed fixed amount for the work and would assume the risk of any fluctuations in costs. Joe Planz, CCC's chief estimator, had prepared estimates of material and labor costs for the project on the basis of the specifications in the drawings. He believed that the material cost would be $1.8 million, plus or minus 10%, and the labor cost would be $650,000, plus or minus 10%. Harman had figured that additional direct overhead (supervision, insurance, taxes, interest on capital tied up with the project, surveys, bonds of performance, etc.) would add an amount totaling 10% of the material and labor costs. Fixed overhead was very small for jobs of this type, about $50,000. Harman knew that CCC was the only firm in the region that would have the expertise for a plant addition of this type. He worried, however, about the possibility of a large Chicago firm taking the job. Increasingly, large Chicago contractors had encroached on regional construction work, particularly in southern Illinois, about 200 miles from the city. He knew that the Chicago firms, because of their union contracts, had 30% higher labor costs than his own nonunion rates, but they had comparable material costs and direct overhead charges. Indirect costs would typically be much higher, as much as $100,000 for a job of this type, because of the large engineering and sales staffs of the Chicago firms. Rumors indicated that the Chicago firms had demanded large profit margins for working so far from headquarters. A profit margin of 10% to 20% was usual, with a figure of 15% being most likely. For fixed-price contracts, firms usually bid on the basis of the expected cost of construction plus profit and a contingency for the risk of taking the job on a fixed-cost basis. For a project of this nature, an appropriate contingency would be 5% of total expected cost. Under the current circumstances, Harman believed he could live with a 7% profit margin. To this figure, the contingency would have to be added. Harman was unwilling to consider a pro forma profit of less than $192,000 (7% of Planz's cost estimate); he preferred to pursue other opportunities if this profit level could not be obtained. (See the attached sample Negotiation Summary form.) Direct Overhead is an overhead charge based on the total of direct labor and materials. It's purpose is to cover the direct costs of the job that are not included in either direct labor or materials used for the job. These include items like supervision, insurance, taxes, site surveys and permits, performance bonds. Fixed Overhead is an overhead charge to cover the fixed costs of the company, for example, office rent, benefits and salaries of the office staff, general liability insurance, utilities, government fees and licenses. It is equitably shared across all jobs of the company, generally based on the total of Direct Costs, and Direct Overhead A contingency fee is an add-on to the total budget if the project is going to be fixed price. It is to compensate for the additional risk the contractor is taking on. A fixed price contract sets a certain amount for the contract. If the contractor does the job for less, he gets to keep the money, but if it costs more, he has to cover the overrun. If the contract is not "fixed price," it is "cost plus." That is, whatever the actual costs are, that is what the principal pays, plus an agreed upon profit margin. The Profit Margin is taken as a percentage of total job costs including Direct Costs, Direct Overhead, and Fixed Overhead. Question: What are your best estimates of the budget ranges for both Centralia and the Chicago firm with following template? YOUR COMPANY PERSPECTIVE FOR CENTRALIA BUDGET Centralia Budget Low Expected Materials Labor Direct Overhead Fixed Overhead Total Project Cost Contingency Budget Profit Grand Total Budget Range YOUR COMPANY PERSPECTIVE FOR CHICAGO FIRM BUDGET Chicago Budget Low Expected Materials Labor Direct Overhead Fixed Overhead Total Project Cost Contingency Budget Profit Grand Total Budget $0 Range $0 Hi Hi As George Harman of Centralia Construction Corporation (CCC) reviewed the drawings and cost estimates for the Myerson Industries plant expansion, he wondered how aggressively he should bid on the project. The current recession had taken a huge bite out of his business, and the Myerson contract would certainly brighten his rather gloomy view of the future. CCC was a family-run, general contracting firm specializing in the construction of commercial structures in south-central Illinois. Founded 30 years ago by George Harman's father, the business had prospered until the recent recession. For the first time in years, there was no backlog of projects, and layoffs had occurred. Although the firm was not in serious financial trouble, more work would be welcomed. Myerson Industries was a highly successful, fast-growing firm specializing in low-cost printers for use with personal computer systems. The Myerson plant was located approximately 50 miles from CCC's offices in Centralia, Illinois. Recently, Roger Myerson had informally inquired if CCC would be interested in bidding on a contract for an addition to the Myerson facility. Harman indicated that he would look forward to the opportunity to submit a bid. Last week the architectural drawings arrived with a cover letter stating that a fixed-price contract would be preferred; that is, the contractor would be paid an agreed fixed amount for the work and would assume the risk of any fluctuations in costs. Joe Planz, CCC's chief estimator, had prepared estimates of material and labor costs for the project on the basis of the specifications in the drawings. He believed that the material cost would be $1.8 million, plus or minus 10%, and the labor cost would be $650,000, plus or minus 10%. Harman had figured that additional direct overhead (supervision, insurance, taxes, interest on capital tied up with the project, surveys, bonds of performance, etc.) would add an amount totaling 10% of the material and labor costs. Fixed overhead was very small for jobs of this type, about $50,000. Harman knew that CCC was the only firm in the region that would have the expertise for a plant addition of this type. He worried, however, about the possibility of a large Chicago firm taking the job. Increasingly, large Chicago contractors had encroached on regional construction work, particularly in southern Illinois, about 200 miles from the city. He knew that the Chicago firms, because of their union contracts, had 30% higher labor costs than his own nonunion rates, but they had comparable material costs and direct overhead charges. Indirect costs would typically be much higher, as much as $100,000 for a job of this type, because of the large engineering and sales staffs of the Chicago firms. Rumors indicated that the Chicago firms had demanded large profit margins for working so far from headquarters. A profit margin of 10% to 20% was usual, with a figure of 15% being most likely. For fixed-price contracts, firms usually bid on the basis of the expected cost of construction plus profit and a contingency for the risk of taking the job on a fixed-cost basis. For a project of this nature, an appropriate contingency would be 5% of total expected cost. Under the current circumstances, Harman believed he could live with a 7% profit margin. To this figure, the contingency would have to be added. Harman was unwilling to consider a pro forma profit of less than $192,000 (7% of Planz's cost estimate); he preferred to pursue other opportunities if this profit level could not be obtained. (See the attached sample Negotiation Summary form.) Direct Overhead is an overhead charge based on the total of direct labor and materials. It's purpose is to cover the direct costs of the job that are not included in either direct labor or materials used for the job. These include items like supervision, insurance, taxes, site surveys and permits, performance bonds. Fixed Overhead is an overhead charge to cover the fixed costs of the company, for example, office rent, benefits and salaries of the office staff, general liability insurance, utilities, government fees and licenses. It is equitably shared across all jobs of the company, generally based on the total of Direct Costs, and Direct Overhead A contingency fee is an add-on to the total budget if the project is going to be fixed price. It is to compensate for the additional risk the contractor is taking on. A fixed price contract sets a certain amount for the contract. If the contractor does the job for less, he gets to keep the money, but if it costs more, he has to cover the overrun. If the contract is not "fixed price," it is "cost plus." That is, whatever the actual costs are, that is what the principal pays, plus an agreed upon profit margin. The Profit Margin is taken as a percentage of total job costs including Direct Costs, Direct Overhead, and Fixed Overhead. Question: What are your best estimates of the budget ranges for both Centralia and the Chicago firm with following template? YOUR COMPANY PERSPECTIVE FOR CENTRALIA BUDGET Centralia Budget Low Expected Materials Labor Direct Overhead Fixed Overhead Total Project Cost Contingency Budget Profit Grand Total Budget Range YOUR COMPANY PERSPECTIVE FOR CHICAGO FIRM BUDGET Chicago Budget Low Expected Materials Labor Direct Overhead Fixed Overhead Total Project Cost Contingency Budget Profit Grand Total Budget $0 Range $0 Hi Hi
Expert Answer:
Answer rating: 100% (QA)
Based on the information provided here are the key considerations for George Harman in determining h... View the full answer
Related Book For
Data Analysis and Decision Making
ISBN: 978-0538476126
4th edition
Authors: Christian Albright, Wayne Winston, Christopher Zappe
Posted Date:
Students also viewed these general management questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
The Crazy Eddie fraud may appear smaller and gentler than the massive billion-dollar frauds exposed in recent times, such as Bernie Madoffs Ponzi scheme, frauds in the subprime mortgage market, the...
-
Read the case study "Southwest Airlines," found in Part 2 of your textbook. Review the "Guide to Case Analysis" found on pp. CA1 - CA11 of your textbook. (This guide follows the last case in the...
-
If Jody's records show $2,000 in investment by owner, $10,000 in net income, $5,000 in assets and $1,000 in owner's drawings. What is Jody's ending owner's equity on a statement of changes in owner's...
-
The flow graph shown in Figure is noncomputable; i.e., it is not possible to compute the output using the difference equations represented by the flow graph because it contains a closed loop having...
-
Refer to Exercise 5-4 and prepare journal entries for Macy Co. to record each of the May transactions. Macy is a retailer that uses the gross method and a perpetual inventory system, and purchases...
-
Shikha Entertainment Ltd. purchased some fixed assets for a consolidated price. The details are as under. Details of the market values of these assets as appraised by a valuer are also given....
-
Thomas is an employer with one employee, Sarah. Sarahs wages are $19,450, and the state unemployment tax rate is 5.4 percent. Calculate the following amounts for Thomas: a. FUTA tax before the state...
-
Use the information below to calculate the machine's depreciation expense Machines initial cost $820 Residual value. $120 The Company started to use the machine on May 1, 2020 The useful fe of the...
-
The Hickory Cabinet and Furniture Company produces sofas, tables, and chairs at its plant in Greensboro, North Carolina. The plant uses three main resources to make furniturewood, upholstery, and...
-
Hope Inc. is a manufacturing company that produces fertilizer for various industrial uses. The standard costs for 1 bag of fertilizer is as follows: Per bag Direct materials (5 g @ $4.00/kg) Direct...
-
In Wisconsin, 30% pass the bar exam on their first try. Of those that take the exam a second time, 40% pass. If you're fresh out of law school, what is the probability of passing the bar within 2...
-
1 12 Type the following code into your coding environment to verify the purposes of the functions. #include void print_star (void); void print_message (void); void main (void) 3 4 5 6 7 8 9 -} 10 11...
-
Show how to build it using 74x138 binary decoders and NAND gates. (1). FA.B.C.D (2,4,7) = = (2). FA.B,C,D (8,11,12,15)
-
Five people are sitting at a table in a restaurant. Two of them order coffee and the other three order tea. The waiter forgot who ordered what and puts the drinks in a random order for the five...
-
you should choose any topic and write the outline by following this way: Introduction Thesis: State in a full sentence your topic, what categories you used for your criteria to judge it, and your...
-
*A wholesaler sells mandarin oranges in boxes of 60. The probability that there are X bad oranges in a box are given in the following table. Value of X 0 1 2 Probability 5k 4k 8k Calculate the value...
-
Interest Compounded Annually. When P dollars is invested at interest rate i, compounded annually, for t years, the investment grows to A dollars, where A = P(1 + i) t . Trevor's parents deposit $7800...
-
Use the RAND function and the Copy command to generate a set of 100 random numbers. a. What fraction of the random numbers are smaller than 0.5? b. What fraction of the time is a random number less...
-
A standardized test consists entirely of multiple-choice questions, each with five possible choices. You want to ensure that a student who randomly guesses on each question will obtain an expected...
-
In the portfolio optimization model, stock 2 is not in the optimal portfolio. Use SolverTable to see whether it ever enters the optimal portfolio as its correlations with stocks 1 and 3 vary....
-
The solar system is like an atom in that both (a) are governed principally through the electric force. (b) consist of a central body surrounded by objects moving in elliptical paths. (c) are composed...
-
Each second, the burning Suns mass (a) increases. (b) remains unchanged. (c) decreases.
-
The nebular theory is based on the observation that the solar system (a) follows patterns indicating that it formed progressively from physical processes. (b) has a structure much like an atom. (c)...
Study smarter with the SolutionInn App