Question: AS is evaluating a project that is expected to generate the following cash flow stream: Expected Cash Flow Now -R 100,000 End-of-year 1 R 50,000
AS is evaluating a project that is expected to generate the following cash flow stream:
Expected Cash Flow
Now -R 100,000
End-of-year 1 R 50,000
End-of-year 2 R 50,000
End-of-year 3 R 50,000
Required:
2.1. If the projects cost of capital is 12 per cent, what is the present value of the projects
expected cash flow stream?
2.2. What is the net present value of the project?