Question: As project manager, you are working on finalizing the costs for all the work packages, activities, control accounts, and contingency reserves. Which document do you
As project manager, you are working on finalizing the costs for all the work packages, activities, control accounts, and contingency reserves. Which document do you produce as a result of this effort?
Project budget
Cost aggregation
C Cost baseline
D WBS