Question: As seen in your course project, several tasks were given a contingency allocation in the budget. Placing these contingencies in the project Budget is an

As seen in your course project, several tasks were given a contingency allocation in the budget. Placing these contingencies in the project Budget is an action to which type of risk response?
Mitigating risks
Exploiting risks
Avoiding risks
Transferring risks