Question: As senior engineer with a medium-sized construction-contracting organisation you are required to put together a tender for a sewer main extension construction project in Southport.

As senior engineer with a medium-sized construction-contracting organisation you are required to put together a tender for a sewer main extension construction project in Southport. Table details your proposed financial schedule with cumulative expenditure and income presented. From this process you determined that the total works cost was $150,000 and the contract price should be $190,000. Consider an Indirect cost 10% of the total Direct cost and needed to distributed uniformly throughout the project life. From the financial details provided in Table:

  1. Develop the month wise cashflow table (you do not need to draw graphs) showing monthly over draft.

  1. Detail the mark-up, average overdraft and maximum overdraft.

Table Financial Expenditure and Income Report

Month

Cumulative Direct Expenditure ($)

Cumulative Income ($)

0

0

0

1

15000

0

2

23,000

22,500

3

47,000

30,000

4

58,000

42,500

5

74,000

59,000

6

80,000

72,000

7

106,000

86,000

8

118,000

100,000

9

135,000

115,000

10

145,000

150,000

11

150,000

180,000

12

150,000

190,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!