Question: As senior engineer with a medium-sized construction-contracting organisation you are required to put together a tender for a sewer main extension construction project in Southport.
As senior engineer with a medium-sized construction-contracting organisation you are required to put together a tender for a sewer main extension construction project in Southport. Table details your proposed financial schedule with cumulative expenditure and income presented. From this process you determined that the total works cost was $150,000 and the contract price should be $190,000. Consider an Indirect cost 10% of the total Direct cost and needed to distributed uniformly throughout the project life. From the financial details provided in Table:
- Develop the month wise cashflow table (you do not need to draw graphs) showing monthly over draft.
- Detail the mark-up, average overdraft and maximum overdraft.
Table Financial Expenditure and Income Report
| Month | Cumulative Direct Expenditure ($) | Cumulative Income ($) |
| 0 | 0 | 0 |
| 1 | 15000 | 0 |
| 2 | 23,000 | 22,500 |
| 3 | 47,000 | 30,000 |
| 4 | 58,000 | 42,500 |
| 5 | 74,000 | 59,000 |
| 6 | 80,000 | 72,000 |
| 7 | 106,000 | 86,000 |
| 8 | 118,000 | 100,000 |
| 9 | 135,000 | 115,000 |
| 10 | 145,000 | 150,000 |
| 11 | 150,000 | 180,000 |
| 12 | 150,000 | 190,000 |