Question: as soon as possible please Time estimates Weeksime ? Activity 03/0B12020 A project is defined to contain following activities, with their timelines Immediate Activity Predecesor

as soon as possible please Time estimates

as soon as possible please

Time estimates Weeksime ? Activity 03/0B12020 A project is defined to contain following activities, with their timelines Immediate Activity Predecesor b A 3 4 5 B . 2 16 D 2 12 D A 12 18 E D 3 15 B,C 6 8 16 EF 1. 5 9 OLAWL (6-a) Expected Time = a +4 mtb 6 "Activity Variance (62) 1. Calculate the expected time & the Variance for each activity 2. Draw network diagram on the basis of Expected Time for each activity. Find out & show Critical Path. 4 Show Early Start, Early finish, Late start & Lat finish for each activity 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!