Question: As the decision maker you are responsible for choosing between the following projects Project Technology Ease of Transition Estimated Cost Savings Vampire High Low High
- As the decision maker you are responsible for choosing between the following projects
| Project |
|
|
|
|
| Technology | Ease of Transition | Estimated Cost Savings |
| Vampire | High | Low | High |
| Dracula | Medium | High | High |
| Witch | High | Medium | Low |
Based on your analysis, which project would you adopt? Why?
- Suppose the information in problem 1 was supplemented with the following rates:
Technology = 3; Ease of Transition = 3; and Estimated Cost Savings = 1.
Also assume that the evaluations of High receive a score of 3; Medium a score of 2; and, Low a score of 1. Which project would you choose now?