Question: As the project manager for a team of software developers, your team has been hired to develop a piece of proprietary software for a corporate

As the project manager for a team of software developers, your team has been hired to develop a piece of proprietary software for a corporate customer. After a few weeks working on the project your customer announces that they must reduce their budget for your project by 15%, but that the software needs to look and function as originally agreed with no changes.
Using the triple constraint model, what trade-off could you use to meet your customer's new requirements?
Change the project goals
Change the timeline
Change the project scope
Change team roles
 As the project manager for a team of software developers, your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!