As the project manager, Kagiso is developing a subsidiary plan of the project management plan that defines the processes, procedures, tools and techniques to effectively engage stakeholders in project decisions and execution based on the analysis of their needs, interests, and potential impact. What is this plan known as
Stakeholder mapping
Stakeholder management plan
Stakeholder analysis
Stakeholder identification plan
Stakeholder engagement plan