As the project manager of a website development project, you have just completed an analysis of project risks and have prioritized them using a probability and impact matrix. The approach you used to prioritize the risks is:
Question 8 options:
a)
Qualitative analysis
b)
Quantitative analysis
c)
Earned value analysis
d)
Sensitivity analysis