Question: As the project manager over a major construction project, you will spend much of your time managing your suppliers. One of your major objectives during
As the project manager over a major construction project, you will spend much of your time managing your suppliers. One of your major objectives during negotiation should be:
obtain a fair and reasonable price
obtain the lowest price possible
ensure your suppliers are taking most to all of the risk
support collusion among all your potential suppliers
You and your team are closing out a contract with one of your suppliers. Formal written notice that the contract has been completed is usually done through:
the project manager
the project teams
the contract administrator
the project sponsors
You have had a contract in place for several years with your sub-contractor, Foster Associates. Over the last few months deliverables have been late and quality low. Management has just decided to terminate this contract. What process will you now enter?
close procurements
close phase or project
verify scope
administer procurements