Question: As the project progresses, the team is not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at
As the project progresses, the team is not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the project. How should the project manager resolve this? Conduct team-building exercises. Make sure that the team has a full understanding of the scope Stop the project and perform a team skill assessment. Escalate a schedule risk to the sponsor