Question: As you are developing your project schedule it is suggested that you use PERT to estimate activity durations. You go to the engineer performing Activity
- As you are developing your project schedule it is suggested that you use PERT to estimate activity durations. You go to the engineer performing Activity A and ask her for her estimates. She states that best case Activity A can be completed in 20 days. Most likely Activity A will take 25 days and worse case it will take 48 days. What is the PERT estimate you should use when building your schedule? (Please show your work)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock