Question: As you are developing your project schedule it is suggested that you use PERT to estimate activity durations. You go to the engineer performing Activity

  1. As you are developing your project schedule it is suggested that you use PERT to estimate activity durations. You go to the engineer performing Activity A and ask her for her estimates. She states that best case Activity A can be completed in 20 days. Most likely Activity A will take 25 days and worse case it will take 48 days. What is the PERT estimate you should use when building your schedule? (Please show your work)