Question: Asmallprojecthas7activitiesandthetimeindaysforeachactivityisgivenonthetable below. Activity ImmediatePredecessor TimeinDays A ....... 2 B ......... 3 C ........... 4 D A 1 E B 2 F B 5 G C
Asmallprojecthas7activitiesandthetimeindaysforeachactivityisgivenonthetable below.
Activity | ImmediatePredecessor | TimeinDays |
| A | ....... | 2 |
| B | ......... | 3 |
| C | ........... | 4 |
| D | A | 1 |
E | B | 2 |
| F | B | 5 |
| G | C | 7 |
| H | D,E | 2 |
| I | F, G | 3 |
| J | H,I | 1 |
Required
Show the logical relationship between the activities in the network diagram and show how long the project take to complete. Show the critical path