Question: assembly line balancing with normal distributed process times. workstation 1 ~ N(22,1) workstation 2 ~ N(25,1) workstation 3 ~ N(25,5) workstation 4 ~ N(16,1) which
assembly line balancing with normal distributed process times.
workstation 1 ~ N(22,1)
workstation 2 ~ N(25,1)
workstation 3 ~ N(25,5)
workstation 4 ~ N(16,1)
which workstation is bottleneck? why?