Question: assembly line balancing with normal distributed process times. workstation 1 ~ N(22,1) workstation 2 ~ N(25,1) workstation 3 ~ N(25,5) workstation 4 ~ N(16,1) which

assembly line balancing with normal distributed process times.

workstation 1 ~ N(22,1)

workstation 2 ~ N(25,1)

workstation 3 ~ N(25,5)

workstation 4 ~ N(16,1)

which workstation is bottleneck? why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!