Question: Assessing and Analyzing Risks 20. Jordanne King, the project manager for Webjets Inter- national, Inc., compiled a table showing time estimates for each of the

Assessing and Analyzing Risks 20. Jordanne King,
Assessing and Analyzing Risks 20. Jordanne King, the project manager for Webjets Inter- national, Inc., compiled a table showing time estimates for each of the activities of a project to upgrade the com- pany's Web page, including optimistic, most likely, and pessimistic. a. Calculate the expected time, te, for each activity. b. Calculate the variance, o?, for each activity. Activity Optimistic (days) Most Likely (days) Pessimistic (days) 3 A 8 19 B 12 15 18 C 2 6 16 D 4 9 20 E 1 4 st 7 21. Recently