Question: Assig? Ring C apter 1 6 ( 1 ) The president of a consulting firm wants to minimize the total number of hours it will

Assig?
Ring C
apter 16(1)
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accors. estimated the time it should take for each of her top consultants - Charlie, Betty, Johnny, and Rick - to complete any of the four projects, as follows:
-1
\table[[,Project (Hours)],[Consultant,A,B,C,D,],[Charlie,13,16,11,13,],[Betty,11,15,14,18,],[Johnny,15,22,12,15,],[Rick,17,17,12,22,]]
Assume there must be one-to-one matching between consultants and projects. After the row and column reductions, what is the resulting entry in the new table for assigning Rick to project D?
Multiple Choice
8 hours
9 hours
10 hour
 Assig? Ring C apter 16(1) The president of a consulting firm

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!