Question: ASSIGN 2 A 1 0 marks Using the data supplied ( items A - X ) create the following: a . On Tab 2 Network

ASSIGN 2A 10 marks
Using the data supplied (items A - X) create the following:
a. On Tab 2 Network - Create a Network diagram showing the relationships of items A-X)
b. On Tab 2 Network - Identify the various paths in the Network and the time each path takes to complete
c. On Tab 2 Network - List and Identify the Critical Path on the Network i.e. A, C, F, etc. A,B,C,D,E,G,H,I,U,V,W,X
d. How long does the project take to complete? 22 Days
Using the information created on Tab 2. create the corresponding Gantt Chart Tab 3. Gantt Chart
a. Clearly identify the critical path
b. Note all non-critical items and the slack or float associated them
c. Start date for the project is January 1,2023
Please feel free to use the template given to you on "How to build a Network and Gantt Chart" as a guide
Submit ASSIGN 2A via the Assignment function in Blackboard:
File Name Format: Assign 2A - Student names.xlsx
Upon Receipt of item 3 above I will mark ASSIGN 2A , make any necessary comments,
and return it to you with several scenario's which will be applied to your Gantt chart.
Any errors/changes identified in ASSIGN 2A need to be made BEFORE you start applying the various scenarios.
ASSIGN 2B 15 Marks
Make any necessary changes recommended from the marking of ASSIGN 2A before proceeding with the various scenarios.
No changes will be required to the Network Diagram for the various scenarios, unless directed in marking of ASSIGN 2A
Save each scenario change as a new Gantt Chart in a separate tab i.e. S-1; S-2 etc. Three scenarios means 3 separate Gantt Charts
File Name Format: Assign 2B - Student names.xlsx
Upon completion of the various scenario givens, attach file to ASSIGN 2B and submit
Full completion and submission by April 8th at the latest - No Extensions
Any additional questions can be asked in the questions Discussion board pr by making an appoint to talk to the Prof.
create a gantt chart as it should be on excel with bars from following data, exclude weekends. Task Name Duration Predecessors
A - Door Mirror Assembly 0 days
B - Design Door Mirror Ass'y 5 days A
C - Door Casing Mold 0 days B
D - Design Casing Mold 2 days C
E - Build Casing Mold 5 days D
F - Purchase Raw Material 2 days D
G - Run Sample Casings 1 day E, F
H - QC Check Sample Casing 1 day G
I - Run Production Casing 3 days H
J - Reflective Mirror 0 days B
K - Mirror - Existing - In Stock 0 days J
L - Camera Interface 0 days B
M - Design Interface 3 days L
N - Build Interface 2 days M
O - Install Interface 1 day N
P - Camera 0 days B
Q - Design Camera 5 days P
R - Electrical Cables - Existing 0 days Q
S - Build Camera 3 days Q, R
T - Test Camera 2 days S
U - Final Assembly 0 days I, K, O, T
V - Door Mirror Assembly 3 days U
W - Inspect Mirror Assembly 1 day V
X - Ship Mirror Assembly 1 day W

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!