Question: ASSIGN 2 A 1 0 marks Using the data supplied ( items A - X ) create the following: a . On Tab 2 Network
ASSIGN A marks
Using the data supplied items A X create the following:
a On Tab Network Create a Network diagram showing the relationships of items AX
b On Tab Network Identify the various paths in the Network and the time each path takes to complete
c On Tab Network List and Identify the Critical Path on the Network ie A C F etc. ABCDEGHI,UVWX
d How long does the project take to complete? Days
Using the information created on Tab create the corresponding Gantt Chart Tab Gantt Chart
a Clearly identify the critical path
b Note all noncritical items and the slack or float associated them
c Start date for the project is January
Please feel free to use the template given to you on "How to build a Network and Gantt Chart" as a guide
Submit ASSIGN A via the Assignment function in Blackboard:
File Name Format: Assign A Student names.xlsx
Upon Receipt of item above I will mark ASSIGN A make any necessary comments,
and return it to you with several scenario's which will be applied to your Gantt chart.
Any errorschanges identified in ASSIGN A need to be made BEFORE you start applying the various scenarios.
ASSIGN B Marks
Make any necessary changes recommended from the marking of ASSIGN A before proceeding with the various scenarios.
No changes will be required to the Network Diagram for the various scenarios, unless directed in marking of ASSIGN A
Save each scenario change as a new Gantt Chart in a separate tab ie S; S etc. Three scenarios means separate Gantt Charts
File Name Format: Assign B Student names.xlsx
Upon completion of the various scenario givens, attach file to ASSIGN B and submit
Full completion and submission by April th at the latest No Extensions
Any additional questions can be asked in the questions Discussion board pr by making an appoint to talk to the Prof.
create a gantt chart as it should be on excel with bars from following data, exclude weekends. Task Name Duration Predecessors
A Door Mirror Assembly days
B Design Door Mirror Ass'y days A
C Door Casing Mold days B
D Design Casing Mold days C
E Build Casing Mold days D
F Purchase Raw Material days D
G Run Sample Casings day E F
H QC Check Sample Casing day G
I Run Production Casing days H
J Reflective Mirror days B
K Mirror Existing In Stock days J
L Camera Interface days B
M Design Interface days L
N Build Interface days M
O Install Interface day N
P Camera days B
Q Design Camera days P
R Electrical Cables Existing days Q
S Build Camera days Q R
T Test Camera days S
U Final Assembly days I, K O T
V Door Mirror Assembly days U
W Inspect Mirror Assembly day V
X Ship Mirror Assembly day W
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock