Question: Assignment 1 - ERP Introduction Work must be completed with MS Excel Develop a gnaterial requirements plan for end item P and its components, given

Assignment 1- ERP Introduction
Work must be completed with MS Excel
Develop a gnaterial requirements plan for end item P and its components, given the tree below.
Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F which is ordered in multiples of 400 units.
One hundred units of P are needed at the start of each of weeks 4 and 8. Beginning inventories are: 20P,100A, and 200F.
Scheduled receipts are: 800F at the start of week 1.
 Assignment 1- ERP Introduction Work must be completed with MS Excel