Question: Assignment 2 CM 3 9 4 Construction Planning and Scheduling ABC Construction Company has the opportunity of constructing a pump station and three sewage stabilization

Assignment 2
CM 394 Construction Planning and Scheduling
ABC Construction Company has the opportunity of constructing a pump station and three sewage stabilization ponds to be located outside of Greensboro City. The Company Scheduling Department has prepared the following list of activities for the project, showing their immediate successors:
\table[[Activity,Description,Succersors,Durati],[100,Mobilization,210,310,400,610,3],[121,Start Pump Station,220,1],[22,Construct Pump Station,230,12],[,Complete Pump Station,240,2],[,Start Up Pump Systems,999,1],[,Clear and Grub Site,320,34,4],[322,Excavate Pond 1,324,5],[24,Shape Pond 1,328,7],[328,Treat/Dress Pond 1,332,9],[3),Test Pond 1,999,2],[on,Excavate Pond 2,344,3],[44,Shape Pond 2,348,5],[,Treat/Dress Pond 2,352,8],[1,Test Pond 2,999,2],[,Excavate Pond 3,364,],[64,Shape Pond 3,368,500,],[en,Treat/Dress Pond 3,372,7],[,Test Pond 3,999,2],[00,Force Main,440,11],[N,Test Force Main,460,17],[,Tie In Force Main,999,],[,Pond Overflow Structure,999,10],[,Roadway Preparation,620,5],[,Construct Base and Pave Road,999,],[,Clean Up and Demobilize,None,]]
The Department manager is asking you, a scheduler, to do the following calculation:
Based on the hand-draw precedence diagram (AON) you did in the Assignment 1, manually calculate DS, DF, LS, LF, TF, and FF for each activity. (70%)
Indicate the project duration and critical path(s) on the AON network. (10%+20%)
Assignment 2 CM 3 9 4 Construction Planning and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!