Question: Assignment 2 CM 3 9 4 Construction Planning and Scheduling ABC Construction Company has the opportunity of constructing a pump station and three sewage stabilization
Assignment
CM Construction Planning and Scheduling
ABC Construction Company has the opportunity of constructing a pump station and three sewage stabilization ponds to be located outside of Greensboro City. The Company Scheduling Department has prepared the following list of activities for the project, showing their immediate successors:
tableActivityDescription,Succersors,DuratiMobilization,Start Pump Station,Construct Pump Station,Complete Pump Station,Start Up Pump Systems,Clear and Grub Site,Excavate Pond Shape Pond TreatDress Pond Test Pond onExcavate Pond Shape Pond TreatDress Pond Test Pond Excavate Pond Shape Pond enTreatDress Pond Test Pond Force Main,NTest Force Main,Tie In Force Main,Pond Overflow Structure,Roadway Preparation,Construct Base and Pave Road,Clean Up and Demobilize,None,
The Department manager is asking you, a scheduler, to do the following calculation:
Based on the handdraw precedence diagram AON you did in the Assignment manually calculate DS DF LS LF TF and FF for each activity.
Indicate the project duration and critical paths on the AON network.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock