Question: Assignment 2 Project Management 12. Draw a network diagram that represents the following IS development task list. Activity Immediate Predecessor 1. Problem Definition 2. Study
Assignment 2 Project Management 12. Draw a network diagram that represents the following IS development task list. Activity Immediate Predecessor 1. Problem Definition 2. Study Current System 1 3. Define User Requirements 1 4. Logical System Design 3 5. Physical System Design 2 6. System Development 4, 5 7. System Testing 6 8. Convert Database 4, 5 9. System Conversion 7, 8 14. Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 30 weeks? Assume that Systems Analysis actually finished at 8 weeks, Design Input & Output actually finished at 15 weeks, and Design Database actually finished at 19 weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 30 weeks? Assume that activity A actually finished at 5 weeks and activity B actually finished at 5 weeks. Recalculate the expected project completion time.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
