Question: Assignment # 3 Complete the following questions found below either in WORD or in a WRITTEN format. Show all your calculations and use the format

Assignment #3
Complete the following questions found below either in WORD or in a WRITTEN format. Show all your calculations and use the format used to solve the In Class Examples.
Format matters in the calculations, deviation from the format highlighted in the class examples will result in a reduction of marks.
Determine the bottleneck (Define it in the comment column) and calculate the Hourly Capacity and Balance Delay at each of the operations. Put your answers in the following chart. Assume that the Net Available Time is equal to 400 min .
Operation Manpower
Cycle Time (Seconds)
Hourly Capacity
Balance Delay Time
Comments 101520163017401105018
Based on the information on the above chart and assuming each operation is tied together with the other one, what would be the Direct Labour cost of the process based on the standard hour? Assume the labour cost is $18 per hour. (Hint: Use the theory of "Bottleneck" operations and "Standard Hours") If you were to decouple this process at, what location would you do it? Why?
Page 1
Assignment #3
Magna International has the following process flow for the manufacturing of one of
their products. The plant runs 3,8 hours shifts, 5 days per week, 240 days per year.
The annual demand is 400,000 units with a 20% cushion required and a 2% scrap
expected (98% yield). The available time consists of total losses of 80 minutes per
shift (includes contractual and downtime) with the predicable downtime being 60
minutes per shift (just breaks and lunches) of the total losses.
Answer the following questions:
a. Calculate the modified volume requirements which include the production
losses and customer requirements.
b. What is the TAKT Time (based on the modified volume)
c. What is the effective hourly capacity based on the Takt Time?
d. What is the bottleneck operation of this process?
e. What is the HOURLY effective capacity of this process?
f. What is the weekly capacity if Magna works 3,8-hour shifts, 5 days er week,
based on the effective capacity? How does this compare to the contract
requirements?
g. If the output of the line averages 6,200 assemblies per week, calculate the
production efficiency.
h. If the bottleneck is broken with the addition of an identical piece of
equipment, what is the new bottleneck operation?
i. What is the new Effective Capacity of this process? Will it meet the
contractual demand requirements? Explain?
j. What is the standard hour for this process using the new process rate if 5
operators are directly assigned to this process.
k. Using the new rate of the process, what is the Direct Labour cost if all are
being paid at $25 per hour.
 Assignment #3 Complete the following questions found below either in WORD

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!