Question: Assignment - Arrow Diagram Technique Draw neatly by hand the arrow diagram for the following projects and determine: A ) Project total duration B )

Assignment - Arrow Diagram Technique
Draw neatly by hand the arrow diagram for the following projects and determine:
A) Project total duration
B) Forward and Backward Passes
C) Calculations - Tabulate your answer
D) Critical Path
Project 1(20 points):
\table[[Activity,Duration,Predecessor],[A,1,-],[B,2,-],[C,3,-],[D,4,A],[E,5,B],[F,6,B],[G,6,C],[H,6,D, E],[I,2,G],[J,3,H, F, I]]
Project 2(20 points):
\table[[Activity,Duration,Predecessor],[A,2,-],[B,4,-],[C,3,-],[D,5,A],[E,8,A, B],[F,6,A, B, C]]
 Assignment - Arrow Diagram Technique Draw neatly by hand the arrow

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!