Question: Assignment Content 1 . A project has been defined to contain the following list of activities along with their required times for completion. Add all
Assignment Content
A project has been defined to contain the following list of activities along with their required times for completion.
Add all activities to a new P project Mini project arrange all dependencies.
a Screenshot of the network diagram.
b Calculate the project duration. write down the answer
c Screenshot of Gantt Chart.
d What would happen if activity were revised to take days instead of day? Provide screenshot for the updated network diagram showing critical path and explain
Look again at the activities outlined in Question Assume that before the project starts, your team discovers that the activity duration estimates were all wrong. Rather than days, Activity will take only two days to complete, whereas both Activities and will take three times longer than originally estimated listed in the table Further, all other activities will take twice as much time listed in the table to complete. In addition, your team has noticed that additional training is needed. This new activity, number will take one day to complete, and after the completion of Activities
a List all activities with their new durations.
b Screenshot of the new network diagram
c Calculate the project duration. write down the answer
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
