Question: Assignment Content 1 . A project has been defined to contain the following list of activities along with their required times for completion. Add all

Assignment Content
1. A project has been defined to contain the following list of activities along with their required times for completion.
Add all activities to a new P6 project Mini project 2, arrange all dependencies.
a. Screenshot of the network diagram.
b. Calculate the project duration. (write down the answer)
c. Screenshot of Gantt Chart.
d. What would happen if activity 6 were revised to take 6 days instead of 1 day? (Provide screenshot for the updated network diagram showing critical path and explain)
2. Look again at the activities outlined in Question 1. Assume that before the project starts, your team discovers that the activity duration estimates were all wrong. Rather than 3 days, Activity 2 will take only two days to complete, whereas both Activities 4 and 7 will take three times longer than originally estimated (listed in the table). Further, all other activities will take twice as much time (listed in the table) to complete. In addition, your team has noticed that additional training is needed. This new activity, number 11, will take one day to complete, and after the completion of Activities 10.
a. List all activities with their new durations.
b. Screenshot of the new network diagram
c. Calculate the project duration. (write down the answer)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!