Question: Assignment Content Read the textbook Page 2 3 3 - 2 3 4 about Precedence diagram 1 . Explain all the relationships ( task dependencies
Assignment Content
Read the textbook Page about Precedence diagram
Explain all the relationships task dependencies in Figure
eg C does not start before A is finished.
A and B can be conducted in parallel. Parallel means the activities do NOT have any dependencies between them.
Screenshot png
Using any software but P draw a precedence diagram using Figure on the textbook as example based on the following information the precede here means immediate precede:
There are ten total tasks, named AJ
Tasks A B and H have durations of two days.
Tasks C E I, and J have durations of three days.
Tasks D F and G have durations of one day.
Tasks A B F and D can be conducted in parallel.
Tasks A and F must precede Task E
Task E must precede Task G
Task C must precede task B
Task B must precede Task H
Task D must precede Task I.
Tasks G H and I may be conducted in parallel.
Tasks G H and I precede Task J
Make sure to add the start node and the end node.
Except for the very first and very last node, every node in the diagram should be connected from both left and right, meaning that they should have both predecessors and successors
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock