Question: Assignment Content The manufacturing process requires 1 4 2 parts per hour. The assembly cell can now respond to an order for a batch of

Assignment Content
The manufacturing process requires 142 parts per hour. The assembly cell can now respond to an order for a batch of parts in three
hours.
The safety stock remains at 15 percent. The parts come in a lot size of 4 units.
How many Kanban cards are needed?
As part of the lean initiative, the company has a lead time to receive the items of 2 hours. How many Kanban cards are needed
now?