Question: Assignment: Earned Value Management Mini Case Study (Modified) Case Study Scenario: You are the project manager for a construction project that involves building and

Assignment: Earned Value Management Mini Case Study (Modified) Case Study Scenario: You

are the project manager for a construction project that involves building and

Assignment: Earned Value Management Mini Case Study (Modified) Case Study Scenario: You are the project manager for a construction project that involves building and installing a series of solar power units for a client. The project was planned to be completed in 8 months at a total cost of AED500,000. You are currently in the 6th month of the project, and you need to assess its progress using Earned Value Management (EVM). Instructions: 1. Calculate the following EVM metrics for your project based on the provided data: Planned Value (PV) Earned Value (EV) Actual Cost (AC) Cost Performance Index (CPI) Schedule Performance Index (SPI) Estimate at Completion (EAC) using both the CPI and SPI methods Variance at Completion (VAC) 2. Additionally, calculate and report the Earned Value for the number of solar power units installed as a separate metric. 3. Provide a brief analysis of the project's performance based on the calculated EVM metrics, focusing on the units installed as well. Data: Planned Budget (BAC): AED500,000 . Planned Duration (8 months): 240 days Actual Cost Incurred: AED420,000 Planned Units to Install: 200 units Units Installed: 150 units Actual Duration (6 months): 180 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!