Question: Assignment Information: Assume you have been asked to build a storage building for a charitable organization that you assist. They have some donated supplies arriving
Assignment Information:
Assume you have been asked to build a storage building
for a charitable organization that you assist. They have
some donated supplies arriving at the end of 15 working
days and desperately need the room in the storage
building you are building to store them. If you are unable
to complete the storage building project in the 15 working days,
it will end up costing the charitable organization (or you, if you feel
guilty enough about it) $100 per day for each day the project takes
longer than 15 working days (because there will be a cost for
storing the donated supplies on the rental truck that is being used
to deliver them).
Information related to this project is as follows:
ID Description Predecessor Time (days)
A Pour Foundation None 3
B Erect frame A 4
C Roof B 4
D Windows B 1
E Doors B 1
F Electrical B 3
G Rough-in Frame C,D,E,F 2
H Door Opener E,F 1
I Paint G,H 2
J Cleanup I 1
REQUIRED:
A. Draw a rough draft of the project network by hand
B. Complete the forward pass
C. Complete the backward pass
D. Compute the activity slack
E. Identify the critical path(s)
F:
Create a Microsoft Word Document (single-spaced, one-inch margins
all around) and give it an appropriate heading (following the format
we have been using for earlier assignments, including assignment number,
student's full name, course numbers, semester, etc.) for Assignment 7.
Put the heading in the upper right-hand corner of the page.
Answer each of the following questions completely. Be sure and number
your responses to correspond to the question numbers below:
(it is a good idea to copy the question into your document
for each before providing your answer and also to be sure
that you provide responses to ALL parts and to all sub-parts
within each question part as requested)
1. What is the Early Finish (EF) time for the last (right-most or right-hand)
activity in the project network? What is the name and the ID of that activity?
2. What is the Late Start (LS) time for activity G (the Rough-In Frame activity)?
3. What is the amount of Slack (SL) for activity D (the Windows activity)?
4. What activities are on the critical path(s)? (List from earliest to latest by
both ID and Activity Name (Description)). What is the total length (in days)
of the critical path? (Hint: the easiest way to display all of the requested information
may be to create a table containing it.)
5. Will the project be done before the end of the 15 working days? If not, for
how many days will the $100 per day of storage on the truck have to be paid
and what will be the total cost for storage?