Question: ASSIGNMENT ONE A work item in a Bill of Quantities is in - situ blinding concrete C 1 5 ( 1 : 3 : 6

ASSIGNMENT ONE
A work item in a Bill of Quantities is in-situ blinding concrete C 15(1:3:6 with 20 mm aggregate) in structural foundations. The volume of concrete to be provided is 200m3 and the method of construction involves site machine mixing. Assume 8 hours working day for plant and gang and 33% for wastage and shrinkage of materials. Assume 25% profit and overhead. The market prices for the materials, labour and plant as well as the plant and labour outputs are as follows:
\table[[Output: Site machine mixing,=,0.25m^(3)/batch],[Mixing cycle of mixer,=,5 minutes],[Operating efficiency of mixer,=,75%],[All-in-plant rate for concrete mixer,,=,],[Poker vibrator all-in-rate,=,GH 300],[One (1) Gang,,\table[[two mason + one],[operator +10 labourers]]],[Output for unloading and stacking of cement (bags/,=,100],[Cost of 1m^(3) of sand (ex-site), GHC,=,100.00],[Cost of 1m^(3) of aggregate (ex-site), GHC,=,170.00],[Cost of 1 bag of cement (ex-site), GHC,=,110],[1m^(3) of cement,,29 bags],[All-in-rate wage of a tradesmen per day, GHC,=,200],[All-in-rate wage of a labourer per day, GH\zeta ,=,150]]
Calculate the following:
(i) Total material cost for 200m3 concrete
(ii) Number of plant days
(iii) Concrete production per day
(iv) Number of bags of cement required for concrete production in a day,
(v) Plant cost for the 200m3 concrete
(vi) Total labour cost for 200m3 concrete
(vii) Total cost for 200m3 concrete including profit and overhead
(viii) Unit Rate (unit cost per m3)
ASSIGNMENT ONE A work item in a Bill of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!